PART A – SHORT ANSWER QUESTIONS
Question 1
Project management theory has some detractors. Explain one argument against planning projects.
What is System 1 and System
2 thinking and how do these systems
impact decision making
in project management? Provide an original example (not one used in
lectures or tutorials) to support your answer.
When undertaking the “lessons learned”
during the project
close stage, what is one approach you could use to explore tacit knowledge?
Explain the approach. Provide an original example or case study (not one used
in lectures or tutorials) to support your answer.
Develop and justify four new tasks aimed at avoiding the cost of non-conformance.
Identify three problems in this Gantt chart and propose solutions
to correct each one.
Question 1
Arguments
against planning projects usually center around the idea that planning is too
rigid and inflexible to be helpful in today's fast-paced, ever-changing
business environment. Critics say that planning takes too much time and effort
up front and can't possibly anticipate all the problems and changes that will
occur throughout a project. They argue that it is better to start working and
deal with problems as they arise.
Question 2
The
impact of effort, uncertainty, and cost of change is felt differently at
different stages of a project life cycle. For example, at the start of a
project, the impact of these factors may be relatively low as the team is still
getting to grips with the project and its requirements. However, as the project
progresses and the team becomes more familiar with the work, the impact of
these factors may increase as the team has a better understanding of the
project and its challenges. Ultimately, at the end of the project, the impact
of effort, uncertainty, and cost of change may be very high, as the team is
under pressure to complete the project and may be facing significant
challenges.
Question 3
System
1 thinking is fast, automatic, and emotional. System 2 thinking is slower, more
deliberative, and more logical. System 1 thinking is more likely to lead to
impulsive decisions, while System 2 thinking is more likely to lead to
thoughtful decisions. For example, imagine you are a project manager and are presented
with two potential solutions to a problem. Solution A is the more
straightforward, intuitive solution, while solution B is more complex and
requires more thought. If you think with System 1, you are more likely to
choose solution A, even if it is not the best option. However, if you are
thinking with System 2, you are more likely to carefully consider both options
and choose the best solution for the situation.
Question 4
The
"Issue Prioritization Matrix" is a tool that helps identify and
prioritize issues during project execution. A simple matrix rates each issue on
two axes - Impact and Probability. This allows the project team to identify and
prioritize the most critical issues quickly.
Question 5
One
approach to exploring tacit knowledge is to conduct semi-structured interviews
with project team members. This involves asking open-ended questions about
the project, what went well, and what could be improved. The aim is to
encourage team members to share their experiences and insights to identify
lessons that can be applied to future projects. For example, a project manager
could interview team members about a recent project that encountered
challenges. The interviews could explore what factors contributed to the
challenges, what could have been done differently, and what lessons were
learned. This information could then be used to improve project planning and
execution on future projects.
Question
6
I
selected the Agile approach for my Assessment 2 project because it is very
iterative and flexible, which I think is well suited to developing a project
management plan. The key advantages of this approach are that it allows for
constant feedback and changes to be made to the plan as the project progresses,
and it is also very adaptable to different project environments. The main
disadvantage of Agile is that it can be challenging to stick to set deadlines
if the project scope is constantly changing. In the future, I would try to be
more disciplined in using Agile and ensure that I still adhere to set deadlines
even if the project scope changes.
Part B
Question 1
A
Gantt chart is a graphical tool that can be used to plan, organize, and track
projects. It is named after its inventor, Henry Gantt, who designed the first
Gantt chart in the early 1900s.Task five is not on the critical path because it
has slack time. This means that it can start later and still not delay the
project. Task eleven also has slack time, so it does not belong on the critical
path.
Question 2
Implement
a quality management system and track quality metrics. Conduct regular audits
of the manufacturing process and products. Invest in training for employees on
quality control procedures. Implement a system for tracking and investigating
customer complaints
Question 3
The
three costs of the Gantt chart are labor, materials, and overhead. The cost
plan for these costs would include the cost of the labor to complete the
project, the cost of the materials needed to complete the project, and the
overhead costs associated with the project. Assumptions related to labor costs
would include the number of workers needed to complete the project, the wage
rate of the workers, and the number of hours needed to complete the project.
Question 4
Problem
1. The
tasks are not correctly sequenced.
2. There is no clear indication of which tasks
depend on others.
3.
There is no clear owner for each task.
1.
Tasks should be sequenced so that dependencies are taken into account.
2.
Tasks should be clearly labeled as dependent or independent.
3.
Each task should have a clear owner.